Chase N Rainbows Real Estate, Inc.

Roofing, Skylights & Solar Panels 8/18-12/5/14 Here is the schedule: Week 1 Skylights; Week 2 & 3 Roof removed & replaced; Week 4 Solar Panels Building 2 Aug. 18 Sept. 12 Units 2A2 and 2B1 Building 3 Sept. 15 Oct. 10 Unit 3A2 Building 1 Oct. 13 Nov. 7 Units 1A2 & 1B1 Building 4 Nov. 10 Dec. 5 Unit 4B2