Chase N Rainbows Real Estate, Inc.

Week 1 Skylights; Week 2 & 3 Roof removed & replaced; Week 4 Solar Panels
Building 2 Aug. 18 Sept. 12 Units 2A2 and 2B1
Building 3 Sept. 15 Oct. 10 Unit 3A2
Building 1 Oct. 13 Nov. 7 Units 1A2 & 1B1
Building 4 Nov. 10 Dec. 5 Unit 4B2
Termite Tenting 1/19-1/22/2015
Unit #2B1 Bathroom remodel May 2014